In November, the natural conditions of Bayannaoerdengkou County are very bad, the wind convolved with sand, more than ten degrees below zero cold, the desert area that is rarely visited, 1 million kilowatts of light storage + ecological governance project is in full swing.
This project involves the installation of 10 Static Var Generator devices in three FGI bid sections. Each bid section has a different project manager of the construction side. The progress of each bid section project is very important, and each bid section has put forward different high standards for our SVG installation work.
As the only project manager of our company on site, Ma Chao was also responsible for promoting the Static Var Generator installation of the three bidding sections. Through his active coordination and communication on site, he implemented the relevant installation work in an orderly manner, and achieved a number of high standards and high quality promotion on the three sites. By tracking the primary cable laying, secondary cable laying, fence foundation making and ground hardening at each site in real time, Ma Chao reasonably adjusted the construction personnel of each bid section, prepared materials in advance, and orderly completed the work tasks such as relevant data preparation, approval and proposal. Timely communication and coordination with the general contractor, civil construction, secondary line construction and supervision of each bid section, to ensure that the construction personnel do not slow down, to achieve a highly satisfactory effect.
The construction party is very much recognized by our Static Var Generator installation work, which has reversed the unfavorable situation in the early stage, and the construction cost has been better controlled. At present, the installation and acceptance of six devices have been completed, and the remaining four are being pushed forward in an orderly manner.